Thanks to Powerscreed rapid, the screed replacement work at the FitX studio in Berlin met all the top performance criteria specified.

Screed replacement under pressure in FitX studio

The screed of a new FitX fitness studio in Berlin was found to be inadequate for the free weights area. Immediate remedial work was essential and needed to be done within the tightest of deadlines – just the job for Powerscreed rapid, MC’s high-performance accelerator for cement screeds.
Screed replacement in FitX studio

Berlin - Germany

The screed of a new FitX fitness studio in Berlin was found to be inadequate for the free weights area. Immediate remedial work was essential and needed to be done within the tightest of deadlines – just the job for Powerscreed rapid, MC’s high-performance accelerator for cement screeds.

Even before the opening of a new studio in Berlin, its operator, Essen-based FitX Deutschland GmbH, was confronted with a major problem: The screed of the approximately 500 m² free weights area on the ground floor had an average flexural strength of only 4 N/mm² instead of the required 7 N/mm². Immediate rehabilitation was necessary – with only a few weeks to go before the planned opening date in August. General contractor André Bahnsch, Managing Director of Bahnsch GmbH, commissioned Sandro Schröder's specialist screed-laying company in Pritzwalk to carry out the work – with an immediate start date. He in turn confidently presented the challenge to MC sales representative Steffen Suenboldt, who was quick to provide the advice and assistance that the screed-laying specialist required.
A screed for special tasks

Not only was the timeline in Berlin extremely tight, the specified F7 flexural strength (7 N/mm²) was also a difficult ask. Achieving such “bending tensile” strength values reliably often poses a problem for earth-moist screeds, due to the fact that compaction is inherently low. However, if the F7 target were to be missed a second time, it would have been a disaster – not least because the subsequent trades were by this time already behind schedule. The solution to the problem? Powerscreed rapid. This high-performance hardening accelerator for the production of screeds that allow early walk-on accessibility and overworking not only saves a great deal of water, it also considerably increases the material’s early and final strength values. Special microcrystals with a cement-like surface structure catalyse the hydration of the cement, accelerating the drying process. In addition, screeds with low w/c values can also be used to good effect.

Thanks to Powerscreed rapid, the screed replacement work at the FitX studio in Berlin met all the top performance criteria specified.

Thanks to Powerscreed rapid, the screed replacement work at the FitX studio in Berlin met all the top performance criteria specified.
© MC-Bauchemie 2018

Customised formulation

Together with screed specialist Schröder, the MC team developed an individual screed mix for this special undertaking. The aim was to ensure that the desired strength would be achieved through increased use of cement combined with the strength-enhancing Powerscreed rapid accelerator. The risk: The application of higher cement ratios can inhibit workability. Yet here, too, Powerscreed rapid showed its capabilities by actually significantly improving the processing properties of the screed, enabling the entire 500 m² area to be completely re-laid in just two days.

 

The site work was further supported by MC to ensure achievement of the required mechanical properties during the drying process. The screed exhibited a flexural strength value of 6.16 N/mm² after ten days and 7.56 N/mm² after 28 days – needless to say, very much to the delight of the screed layers, the site manager and the client alike. And the studio did indeed open on schedule in August 2018.

Related content

References
Magazine
MC-Pedia
Contact
News
Cookie settings

We are continuously improving our website and we use cookies for this purpose. For an optimal user experience, we recommend that you accept them. Otherwise, parts of the page will be deactivated in the display in accordance with data protection regulations.

Essential

Essential cookies for the website to work properly.

Always active
Analytics

We collect data in order to analyze user behavior on the site. This data will be evaluated to provide a better user experience and make you find what you need faster and easier.

Marketing

We analyze marketing data, for example if you found our site through a marketing campaign. We provide information about success or abandoned carts to better understand if you are interested in a certain product or not.

Comfort

Services that make using our site easier but that are not technically necessary. This includes Google Maps for easy location information, YouTube for embedded videos but also the use of contact forms, which are protected from Spam Using Google ReCaptcha.